NEW QUESTION # 29
During what phase should a baseline of the Evolving Solution be put into operational use?
- A. Post-Project
- B. Evolutionary Development
- C. Deployment
- D. Foundations
Answer: C
NEW QUESTION # 30
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.
- A. Champion
- B. Governor
- C. Visionary
- D. director
Answer: C
NEW QUESTION # 31
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
- A. Business Ambassador
- B. Workshop Facilitator
- C. Business Visionary
- D. Business Analyst
Answer: B
Explanation:
The role that should ideally be independent of the outcome to be achieved in a Facilitated Workshop is the Workshop Facilitator4. This role manages the processes and dynamics of the workshop and should remain neutral and impartial4.
NEW QUESTION # 32
Who is responsible for the application of Principle 8, Demonstrate Control?
- A. Team Leader
- B. The project-level roles
- C. Collectively applied by the whole team
- D. Project Manager
Answer: C
NEW QUESTION # 33
What phase will create Solution increments?
- A. Evolutionary Development
- B. Feasibility
- C. Deployment
- D. Foundations
Answer: A
Explanation:
Solution increments are created during the Evolutionary Development phase. This phase is where the solution is developed iteratively, building on the firm foundations laid out in the previous phases1. It involves creating increments of the product through time-boxed iterations, ensuring that the solution evolves in line with the project's objectives and business needs.
NEW QUESTION # 34
What DSDM Principles requires the transparency of all work being performed by the team?
- A. Principle 8-Demonstrate Control
- B. Principle 66-Develop iteratively
- C. Principle 1 - Build incrementally from Firm Foundations
- D. Principle 1- Focus on the Business Need
Answer: A
Explanation:
Principle 8 - Demonstrate Control requires the transparency of all work being performed by the team5. This principle ensures that plans and progress are visible to all and that progress is measured through the delivery of products rather than completed activities5.
NEW QUESTION # 35
Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?
- A. Evolutionary Development
- B. Feasibility
- C. Pre-Project
- D. Foundations
Answer: D
NEW QUESTION # 36
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.
- A. Viewed in light of the overriding project goal
- B. Made collaboratively
- C. The responsibility of the Business Sponsor
- D. Share between all of the project roles
Answer: B
NEW QUESTION # 37
Which practice provides an interactive environment in which all key players can contribute to the outcome?
- A. Facilitied Wordshop
- B. Iterative Development
- C. Timeboxing
- D. Modelling
Answer: A
Explanation:
A Facilitated Workshop provides an interactive environment where all key players can contribute to the outcome3. It is a practice within Agile and DSDM that encourages collaboration and active participation from all stakeholders to shape the project's direction and solutions.
NEW QUESTION # 38
When should the quality of the evolving solution first be tesed?
- A. At the end of a Timebox
- B. As part of the iterative Development process
- C. At the end of a project.
- D. At the end of each increment
Answer: B
NEW QUESTION # 39
When using the Iterative Development technique, which of the following should each cycle include?
1. Though
2. Action
3. Control
4. Conversation
- A. 1, 2, 4
- B. 1, 2, 3
- C. 2, 3, 4
- D. 1, 3, 4
Answer: D
NEW QUESTION # 40
In what phase is it first established whether further investigation of the project is justified?
- A. Evolutionary Development
- B. Feasibility
- C. Foundations
- D. Pre-Project
Answer: B
Explanation:
It is during the Feasibility phase that it is first established whether further investigation of the project is justified3. This phase aims to determine if the proposed project is likely to be feasible from both a technical and business perspective.
NEW QUESTION # 41
Which statement about DSDM roles is true?
- A. In DSDM, one person must hold several roles
- B. DSDM roles should NOT be split between two people
- C. One DSDM roles does NOT necessarily mean one person
- D. All DSDM roles should be shared
Answer: C
Explanation:
In DSDM, it is true that one DSDM role does not necessarily mean one person. This allows for flexibility in assigning roles based on the project's needs and the individuals' skills and capacities. It is possible for one person to hold multiple roles or for a role to be shared among several people, depending on what is most effective for the project.
NEW QUESTION # 42
How is Quality ensured during Evolutionary Development?
- A. By facilitating session to enable a group to work to achieve an agreed goal
- B. By managing objectives in a fixed time period
- C. By continuous verification
- D. By understanding and managing priorities
Answer: C
Explanation:
Quality during Evolutionary Development is ensured by continuous verification2. This involves iterative development, where all development processes, including testing, are repeated to ensure the output is complete and able to generate useful feedback2.
NEW QUESTION # 43
Which purpose relates to the instrumental Success Factors?
- A. Underpins the prioritization of requirements
- B. Informs the development of the Business Case
- C. Inform the development of the Terms of Reference
- D. Positions DSDM projects for a successful outcome
Answer: B
NEW QUESTION # 44
Who is responsible for the application of Principle 8, Demonstrate Control?
- A. Team Leader
- B. The project-level roles
- C. Collectively applied by the whole team
- D. Project Manager
Answer: C
Explanation:
The application of Principle 8, Demonstrate Control, is collectively applied by the whole team4. This principle ensures that there are proper levels of planning, progress measurement, and reporting in place.
NEW QUESTION # 45
Which of the following statements about the technical Coordinator role is true?
The technical Coordination provides the same function from a technical perspective as the Business Ambassador does from a business perspective.
The technical Coordinator is responsible for ensuring that the solution confirm to the requested technical standards.
- A. Neither 1 or 2 is true
- B. Only 1 is true
- C. Only 2 is true
- D. Both 1 and 2 are true
Answer: C
NEW QUESTION # 46
During what phase should the strategy for Iterative Development be considered?
- A. Evolutionary Development
- B. Feasibility
- C. Pre-Project
- D. Foundations
Answer: D
NEW QUESTION # 47
How does DSDM differ from most other Agile approaches?
- A. It focuses on the collaborative working of teams
- B. It focuses on the delivery of products
- C. It focuses on the entire project lifecycle
- D. It focuses on the development of products
Answer: C
Explanation:
DSDM differs from most other Agile approaches because it focuses on the entire project lifecycle456. This includes pre-project, feasibility, foundations, development, and deployment phases, ensuring a comprehensive approach to project management.
NEW QUESTION # 48
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?
- A. Team Leader
- B. Business Visionary
- C. Business Analyst
- D. Technical Coordinator
Answer: B
Explanation:
The Business Visionary is responsible for interpreting the needs of the Business Sponsor and communicating these to the team1. This role represents the Business Sponsor by communicating the vision of the project and ensuring that the team understands the sponsor's requirements1.
NEW QUESTION # 49
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
- A. Management Approach Definition
- B. Terms of Reference
- C. Foundation Summary
- D. Delivery Plan
Answer: C
NEW QUESTION # 50
When initially creating MoSCoW priorities, what is the primary focus?
- A. Project priorities
- B. Iterative Development priorities
- C. Project increment priorities
- D. Timebox priorities
Answer: A
NEW QUESTION # 51
How should DSDM team measure progress?
- A. Based on the completion of activities rather than the delivery of products
- B. Through an analysis of the Instrumental Success Factors.
- C. Based on what has been delivered at the end of a Timebox.
- D. Through a project dashboard
Answer: C
NEW QUESTION # 52
......